Economic Comparison
Manual Cable Bolting/Mechanized Cable Bolting

Data from a lead/zinc mine, using the cut and fill method. Cable bolting of an area in the ore body, 3 slices containing 62.000 tonne of ore (average ore value SEK 373/tonne, total SEK 23.126.000).

75 holes (51 mm 2" dia) 14 m (46 ft) long = 1.050 m (3,444 ft).

Performance:
• Manually 387.5 hours = 48.4 shifts = 16.1 days (3 shift/day)
• Mechanized 61.8 hours = 7.7 shifts = 2.6 days (3 shift/day)

Reinforcements costs Manual Mechanized
Personnel costs
(SEK 135/h, USD 17/h)
52.313 (USD 6.458) 8.343 (USD 1.030)
Drill steel 16.413 (USD 2.026) 16.413 (USD 2.026)
Grout etc. 3.500 (USD 432) 3.500 (USD 432)
Cable 7.350 (USD 907) 7.350 (USD 907)
Cable Bolting equipment
(net investment
SEK 1.800.000 (USD 222.000)
pay off 50.000m, 164.000ft, holes)
- 37.800 (USD 4.667)
Maintenance costs - 3.150 (USD 389)
Total 79.576 (USD 9.824)
75.78/m (USD 30.7/ft)
76.556 (USD 9.451)
72.90/m (USD 29.5/ft)

Cost for the mined ore:
• Manually 180 x 18 x 75.78 = 245.592 = 3,96 tonne ore (USD 0,498/tonne)
• Mechanized 180 x 18 x 72.90 = 236.196 = 3,80 tonne ore (USD 0,469/tonne)


Swedengineers Minetech AB, www.swedengineers.commail@swedengineers.com