Economic Comparison - Mechanized Cable Bolting

Alternative 1:
The mechanized cable bolting is carried out with a unit mounted on a used loader, lorry or truck. Drilling is performed by a production drilling machine, that can be used for production drilling too, when there is no cable bolting job.

Average total capacity: 250 m/shift (820 ft/shift)

Alternative 2:
The mechanized cable bolting is made with a unit that drills, groutes and inserts, with equipment mounted on the same boom. This can not be used for production drilling.

Average total capacity: 100 m/shift (328 ft/shift)

Investment cost:
The same for the two alternatives (complete bolter versus bolter + production drill rig).

Interest rate: (used for calculation) 10%

Production and maintenance costs USD 2-4 for both units

Annual
production
Alternative No shift Financial costs Labour costs Difference
10.000m 1
2
40
100
USD 7.765
USD 19.400
USD 1.930*
USD 2.400
-
+USD 12.105
20.000m 1
2
80
200
USD 10.700
USD 19.400
USD 3.999*
USD 4.800
-
+USD 9.600
30.000m 1
2
120
300
USD 13.600
USD 19.400
USD 5.800*
USD 7.200
-
+USD 7.200

* In alternative 1 the wage is calculated for 1 operator for drilling and 1 operator bolting. In alternative 2, 1 operator is doing both drilling and cable bolting.

RESULT
Because of the multiuse of the drilling unit and more than twice the capacity for alternative 1, this alternative to be recommended.